United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project J807, Lafayette County

Onshore wind project J807, Lafayette County is a 41.4 MW onshore wind request withdrawn in the MISO interconnection queue, in Lafayette County, Wisconsin, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedMay 2020 (project stopped here)
  3. ConsentedOct 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J807
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Darlington - Hillman 138kV Line (Falcon Substation J395)
Location
Lafayette County, Wisconsin
Technology
Wind: 41.4 MW
Total requested
41.4 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Withdrawn
Queue status
Withdrawn
Entered queue
16 June 2017
Agreement signed
17 October 2019
Proposed online date
August 2021
Withdrawn
May 2020

Location

Marker shows the centre of Lafayette County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Lafayette County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem