ONSHORE WIND Β· MISOOnshore wind project J1512, Lafayette County
Onshore wind project J1512, Lafayette County is a 98.9 MW onshore wind request withdrawn in the MISO interconnection queue, in Lafayette County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedDec 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1512
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Darlington 138KV
- Location
- Lafayette County, Wisconsin
- Technology
- Wind: 98.9 MW
- Total requested
- 98.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 19 June 2020
- Proposed online date
- September 2023
- Withdrawn
- December 2021
Location
Marker shows the centre of Lafayette County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Lafayette County
- Onshore wind project J1773, Lafayette CountyOnshore wind Β· 300 MW Β· agreement signed
- Surplus; ALTE.QUILTBLCKBattery storage Β· 98.0 MW Β· in study
- Onshore wind project J652, Lafayette CountyOnshore wind Β· 98.0 MW Β· built
- Onshore wind project J395, Lafayette CountyOnshore wind Β· 98.0 MW Β· built
- Onshore wind project J819, Lafayette CountyOnshore wind Β· 99.9 MW Β· withdrawn
- Onshore wind project J109, Lafayette CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Onshore wind project G282, Lafayette CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Onshore wind project G995, Lafayette CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Onshore wind project G749, Lafayette CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Onshore wind project J807, Lafayette CountyOnshore wind Β· 41.4 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem