Solar project J3470, Tuscola County Solar |
100 MW | In study |
Tuscola, MI | MISO |
Apr 2024 | target 2027 |
Solar project J1706, Green County Solar |
100 MW | Agreement signed |
Green, WI | MISO |
Jun 2020 | target 2028 |
Onshore wind project J2097, Morton County Onshore wind |
100 MW | In study |
Morton, ND | MISO |
Aug 2021 | target 2025 |
Solar project J1714, Fayette County Solar |
100 MW | In study |
Fayette, IL | MISO |
Jun 2020 | target 2026 |
Replacing 100 MW of Solar with storage; J1386 Battery storage |
100 MW | In study |
Lake, IN | MISO |
Jul 2025 | target 2028 |
Solar project J903, Henry County Solar |
100 MW | Under construction |
Henry, IN | MISO |
Jun 2017 | target 2023 |
Solar project J1131, Scott County Solar |
100 MW | Under construction |
Scott, IA | MISO |
Mar 2018 | target 2024 |
Solar + storage project J2069, Montcalm County Solar + storage |
100 MW | In study |
Montcalm, MI | MISO |
Nov 2021 | target 2027 |
Battery storage project J2499, Ottawa County Battery storage |
100 MW | In study |
Ottawa, MI | MISO |
Sep 2022 | target 2026 |
Solar project J3466, Winnebago County Solar |
100 MW | In study |
Winnebago, WI | MISO |
Apr 2024 | target 2028 |
Solar project J1251, Marquette County Solar |
100 MW | Under construction |
Marquette, MI | MISO |
Apr 2019 | target 2025 |
Battery storage project J2120, Linn County Battery storage |
100 MW | In study |
Linn, IA | MISO |
Aug 2021 | target 2025 |
Solar project J1171, Dodge County Solar |
100 MW | Under construction |
Dodge, WI | MISO |
Mar 2018 | 2024 |
Solar project J2296, Sullivan County Solar |
100 MW | In study |
Sullivan, IN | MISO |
Mar 2022 | target 2025 |
Solar project J2808, Fayette County Solar |
100 MW | In study |
Fayette, IL | MISO |
Sep 2022 | target 2026 |
Solar project J1514, Mississippi County Solar |
100 MW | Under construction |
Mississippi, AR | MISO |
Dec 2021 | 2024 |
Solar project J1369, Dubois County Solar |
100 MW | Agreement signed |
Dubois, IN | MISO |
Apr 2019 | target 2025 |
Battery storage project J2555, Ingham County Battery storage |
100 MW | In study |
Ingham, MI | MISO |
Aug 2023 | target 2026 |
Solar project J1392, Lagrange County Solar |
100 MW | Agreement signed |
Lagrange, IN | MISO |
Apr 2019 | target 2025 |
Solar project J908, Tallahatchie County Solar |
100 MW | Under construction |
Tallahatchie, MS | MISO |
Jun 2017 | target 2023 |
Solar + storage project J3231, Amite County Solar + storage |
100 MW | In study |
Amite, MS | MISO |
Sep 2022 | target 2024 |
Battery storage project J2197, Clay County Battery storage |
100 MW | In study |
Clay, IL | MISO |
Jan 2025 | target 2024 |
Battery storage project J1844, Washtenaw County Battery storage |
100 MW | In study |
Washtenaw, MI | MISO |
Dec 2020 | target 2024 |
Solar project J871, Grant County Solar |
100 MW | Under construction |
Grant, WI | MISO |
Jun 2017 | 2023 |
Solar + storage project J2456, Phillips County Solar + storage |
100 MW | In study |
Phillips, AR | MISO |
Sep 2022 | target 2027 |
Solar project J1736, Dubois County Solar |
100 MW | In study |
Dubois, IN | MISO |
Jun 2020 | target 2023 |
Solar project J2739, Ohio County Solar |
100 MW | In study |
Ohio, KY | MISO |
Sep 2022 | target 2026 |
Solar project J2742, White County Solar |
100 MW | In study |
White, AR | MISO |
Sep 2022 | target 2026 |
Onshore wind project J898, Howard County Onshore wind |
100 MW | Under construction |
Howard, IA | MISO |
Jun 2017 | target 2023 |
Onshore wind project J2048, Benton County Onshore wind |
100 MW | In study |
Benton, IN | MISO |
Mar 2022 | target 2025 |
Solar project J3130, Marion County Solar |
100 MW | In study |
Marion, IL | MISO |
Sep 2022 | target 2026 |
Solar project J2679, Livingston County Solar |
100 MW | In study |
Livingston, MI | MISO |
Sep 2022 | target 2027 |
Solar project J4158, Dewitt County Solar |
100 MW | In study |
Dewitt, IL | MISO |
Oct 2025 | target 2030 |
Battery storage project J1635, Branch County Battery storage |
100 MW | Agreement signed |
Branch, MI | MISO |
Jun 2020 | target 2025 |
Surplus; J758 Other |
100 MW | In study |
Calhoun, MI | MISO |
Aug 2024 | target 2027 |
Solar + storage project J2193, Waushara County Solar + storage |
100 MW | In study |
Waushara, WI | MISO |
Nov 2021 | target 2024 |
Surplus; J1190 Battery storage |
100 MW | In study |
Lagrange, IN | MISO |
Jul 2025 | target 2027 |
Solar project J1795, Acadia Parish County Solar |
100 MW | In study |
Acadia Parish, LA | MISO |
Jun 2020 | target 2025 |
Battery storage project J2195, Fayette County Battery storage |
100 MW | In study |
Fayette, IL | MISO |
Jan 2025 | target 2024 |
Other project J4183 Other |
99.9 MW | In study |
| MISO |
| target 2027 |
Solar project J1232, Coles County Solar |
99.0 MW | Agreement signed |
Coles, IL | MISO |
Apr 2019 | target 2025 |
Battery storage project J4172, Wapello County Battery storage |
99.0 MW | In study |
Wapello, IA | MISO |
Oct 2025 | target 2028 |
Solar project J1266, Marion County Solar |
99.0 MW | Agreement signed |
Marion, IL | MISO |
Apr 2019 | target 2025 |
Solar project J1294, Sunflower County Solar |
99.0 MW | Under construction |
Sunflower, MS | MISO |
Apr 2019 | 2024 |
Onshore wind project J1483, Iowa County Onshore wind |
99.0 MW | Agreement signed |
Iowa, WI | MISO |
Apr 2019 | target 2026 |
Solar project J1993, Columbia County Solar |
99.0 MW | In study |
Columbia, WI | MISO |
Dec 2021 | target 2025 |
Solar project J2208, De Soto Parish County Solar |
99.0 MW | In study |
De Soto Parish, LA | MISO |
Aug 2021 | target 2024 |
Onshore wind project J1508, Marathon County Onshore wind |
98.9 MW | Agreement signed |
Marathon, WI | MISO |
Jun 2020 | target 2026 |
Replacing 95 MW of coal with BESS; Meramec 1, 2, 3, 4 Other |
98.8 MW | In study |
St. Louis, MO | MISO |
Dec 2024 | target 2025 |
Solar project J1377, Rock County Solar |
98.6 MW | Agreement signed |
Rock, WI | MISO |
Apr 2019 | target 2025 |