🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J2679, Livingston County

Solar project J2679, Livingston County is a 100 MW solar request in interconnection study in the MISO interconnection queue, in Livingston County, Michigan, connecting to ITC.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2679
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC
Connection point (POI)
COLFAX to Madrid 120 kV
Location
Livingston County, Michigan
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
14 September 2022
Proposed online date
April 2027

Location

Marker shows the centre of Livingston County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Livingston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem