United States › Grid › Interconnection queues › Michigan
SOLAR · MISOSolar project J2485, Livingston County
Solar project J2485, Livingston County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Livingston County, Michigan, connecting to ITC.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2485
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC
- Connection point (POI)
- BLACKFOOT - MADRID 345.0kV
- Location
- Livingston County, Michigan
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- November 2025
Location
Marker shows the centre of Livingston County; the queue data does not give exact sites.
Other requests in Livingston County
- Gas project J3799, Livingston CountyGas · 1,452 MW · in study
- Solar + storage project J2139, Livingston CountySolar + storage · 250 MW · in study
- Solar project J1917, Livingston CountySolar · 165 MW · in study
- Battery storage project J2997, Livingston CountyBattery storage · 160 MW · in study
- Solar project J3858, Livingston CountySolar · 110 MW · in study
- Solar project J2679, Livingston CountySolar · 100 MW · in study
- Other project G217 CONS 94, Livingston CountyOther · 510 MW · withdrawn
- Other project G216 CONS 110, Livingston CountyOther · 280 MW · withdrawn
- Solar project J1911, Livingston CountySolar · 200 MW · withdrawn
- Gas project J427, Livingston CountyGas · 110 MW · withdrawn
- Solar project J1925, Livingston CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem