Solar project J908, Tallahatchie County

Solar project J908, Tallahatchie County is a 100 MW solar request under construction in the MISO interconnection queue, in Tallahatchie County, Mississippi, connecting to Entergy.

Queue statusUnder construction
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedMar 2020 (completed)
  3. Construction (current stage)
  4. OperatingTarget Jun 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J908
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
Webb 115kV Substation
Location
Tallahatchie County, Mississippi
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
16 June 2017
Agreement signed
4 March 2020
Proposed online date
June 2023

Location

Marker shows the centre of Tallahatchie County; the queue data does not give exact sites.

Power plants in Mississippi · Transmission lines in Mississippi

Other requests in Tallahatchie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem