United States › Grid › Interconnection queues › Mississippi
SOLAR · MISOSolar project J908, Tallahatchie County
Solar project J908, Tallahatchie County is a 100 MW solar request under construction in the MISO interconnection queue, in Tallahatchie County, Mississippi, connecting to Entergy.
Queue statusUnder construction
- PlanningQueued Jun 2017 (completed)
- ConsentedMar 2020 (completed)
- Construction (current stage)
- OperatingTarget Jun 2023 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J908
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy
- Connection point (POI)
- Webb 115kV Substation
- Location
- Tallahatchie County, Mississippi
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 16 June 2017
- Agreement signed
- 4 March 2020
- Proposed online date
- June 2023
Location
Marker shows the centre of Tallahatchie County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Tallahatchie County
- Surplus; J908Battery storage · 100 MW · in study
- Onshore wind project J2964, Tallahatchie CountyOnshore wind · 220 MW · withdrawn
- Onshore wind project J4064, Tallahatchie CountyOnshore wind · 200 MW · withdrawn
- Solar project 390, Tallahatchie CountySolar · 200 MW · withdrawn
- Solar project J2391, Tallahatchie CountySolar · 100 MW · withdrawn
- Solar project J2182, Tallahatchie CountySolar · 100 MW · withdrawn
- Solar project 391, Tallahatchie CountySolar · 66.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem