Surplus; J908

Surplus; J908 is a 100 MW battery storage request in interconnection study in the MISO interconnection queue, in Tallahatchie County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1116
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
WEBB
Location
Tallahatchie County, Mississippi
Technology
Battery: 100 MW
Total requested
100 MW
Queue status
Active
Entered queue
31 August 2025
Proposed online date
June 2027

Location

Marker shows the centre of Tallahatchie County; the queue data does not give exact sites.