United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J1251, Marquette County

Solar project J1251, Marquette County is a 100 MW solar request under construction in the MISO interconnection queue, in Marquette County, Michigan, connecting to American Transmission Co..

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedSep 2022 (completed)
  3. Construction (current stage)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1251
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Arnold - Perkins 138 kV Line Tap
Location
Marquette County, Michigan
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
8 September 2022
Proposed online date
June 2025

Location

Marker shows the centre of Marquette County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Marquette County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem