Gas project J3756, Marquette County

Gas project J3756, Marquette County is a 4.2 MW gas request in interconnection study in the MISO interconnection queue, in Marquette County, Michigan, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2019 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3756
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Huron
Location
Marquette County, Michigan
Technology
Gas: 4.2 MW
Total requested
4.2 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
17 April 2024
Proposed online date
January 2019

Location

Marker shows the centre of Marquette County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Marquette County