United States › Grid › Interconnection queues › Michigan
GAS · MISOGas project J3756, Marquette County
Gas project J3756, Marquette County is a 4.2 MW gas request in interconnection study in the MISO interconnection queue, in Marquette County, Michigan, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2019 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3756
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Huron
- Location
- Marquette County, Michigan
- Technology
- Gas: 4.2 MW
- Total requested
- 4.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 17 April 2024
- Proposed online date
- January 2019
Location
Marker shows the centre of Marquette County; the queue data does not give exact sites.
Other requests in Marquette County
- Solar project J1750, Marquette CountySolar · 150 MW · under construction
- Solar project J1251, Marquette CountySolar · 100 MW · under construction
- Solar project J2029, Marquette CountySolar · 62.5 MW · in study
- Gas project J703, Marquette CountyGas · 128 MW · built
- Gas project J394, Marquette CountyGas · 327 MW · withdrawn
- Gas project J413, Marquette CountyGas · 243 MW · withdrawn
- Gas project J398, Marquette CountyGas · 204 MW · withdrawn
- Onshore wind project G750, Marquette CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J3281, Marquette CountyOnshore wind · 170 MW · withdrawn
- Gas project J397, Marquette CountyGas · 153 MW · withdrawn
- Onshore wind project J470, Marquette CountyOnshore wind · 150 MW · withdrawn
- Gas project J317, Marquette CountyGas · 112 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem