United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J871, Grant County

Solar project J871, Grant County is a 100 MW solar request under construction in the MISO interconnection queue, in Grant County, Wisconsin, connecting to American Transmission Co..

Queue statusUnder construction
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedFeb 2020 (completed)
  3. Construction (current stage)
  4. OperatingDec 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J871
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Eden - Wyoming Valley 138kV Line Tap
Location
Grant County, Wisconsin
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
16 June 2017
Agreement signed
21 February 2020
Proposed online date
August 2021
Came online
December 2023

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem