United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project J139, Grant County

Onshore wind project J139, Grant County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Grant County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2009 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. ConsentedAug 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J139
Grid region
MISO (Midcontinent)
Connection point (POI)
Gran Grea - Nelson Dewey 161 kV
Location
Grant County, Wisconsin
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
12 October 2009
Agreement signed
20 August 2012
Withdrawn
August 2012

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem