United States › Grid › Interconnection queues › Wisconsin

ONSHORE WIND · MISO

Onshore wind project J855, Grant County

Onshore wind project J855, Grant County is a 100 MW onshore wind request under construction in the MISO interconnection queue, in Grant County, Wisconsin, connecting to American Transmission Co..

Queue statusUnder construction
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedNov 2019 (completed)
  3. Construction (current stage)
  4. OperatingApr 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J855
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Lancaster - Eden 138 kV Line Tap
Location
Grant County, Wisconsin
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
16 June 2017
Agreement signed
14 November 2019
Proposed online date
November 2020
Came online
April 2023

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem