United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESInterconnection queue in the USA (2016 requests) โ page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Tri-County Solar Solar |
178 MW | Paused / redesign |
| Onshore wind project GEN-2016-128, Alfalfa County Onshore wind |
176 MW | Agreement signed |
| Grandfalls Solar Solar + storage ยท Nextera |
176 MW | Agreement signed |
| Onshore wind project GEN-2016-146, Texas County Onshore wind |
175 MW | Agreement signed |
| Onshore wind project GEN-2016-145, Texas County Onshore wind |
175 MW | Agreement signed |
| Solar project J643, Jasper County Solar |
175 MW | Agreement signed |
| Solar project J586, Mississippi County Solar |
175 MW | Agreement signed |
| Solar project 16-058, Jefferson County Solar |
150 MW | Paused / redesign |
| Onshore wind project GEN-2016-102, Pontotoc County Onshore wind |
148 MW | Agreement signed |
| Solar project 305, Fayette County Solar |
147 MW | Agreement signed |
| Monte Alto I Onshore wind ยท Terra-Gen |
142 MW | Agreement signed |
| Solar project J641, Morgan County Solar |
140 MW | Agreement signed |
| Heritage Wind Onshore wind ยท Heritage Wind, LLC |
126 MW | In study |
| Vinton Solar Solar |
125 MW | Agreement signed |
| Sycamore Creek Solar Solar |
117 MW | Agreement signed |
| Mulqueeney Ranch Wind Onshore wind |
114 MW | Agreement signed |
| Solar project GEN-2016-121, Lea County Solar |
110 MW | Agreement signed |
| Solar project J644, Greene County Solar |
110 MW | Agreement signed |
| Solar project G0527, Lake County Solar |
105 MW | In study |
| Solar project 734, Crook County Solar ยท Aurora Solar, LLC |
102 MW | Agreement signed |
| Kyan Solar Solar |
102 MW | Agreement signed |
| Holstein 2 Solar Solar + storage ยท 229HD 8me LLC |
101 MW | In study |
| Solar project GEN-2016-030, Johnston County Solar |
100 MW | Agreement signed |
| Onshore wind project GEN-2016-139, Texas County Onshore wind |
100 MW | Agreement signed |
| Solar project G0532, Morrow County Solar |
100 MW | In study |
| Solar project J603, Ashley County Solar |
100 MW | Agreement signed |
| Solar project J552, Lee County Solar |
100 MW | Agreement signed |
| Onshore wind project 786, Summit County Onshore wind ยท Echo Divide Wind, LLC |
100 MW | Agreement signed |
| Solar project J680, Ashley County Solar |
100 MW | Under construction |
| Solar project J604, Sunflower County Solar |
100 MW | Agreement signed |
| Onshore wind project J569, Rock County Onshore wind |
100 MW | Agreement signed |
| Greenwood Solar Solar |
100 MW | Agreement signed |
| Onshore wind project GEN-2016-087, Campbell County Onshore wind |
98.9 MW | Agreement signed |
| Solar project 805, Kane County Solar ยท Glen Canyon Solar A, LLC |
95.0 MW | In study |
| Waypost Solar Project Solar |
92.0 MW | Paused / redesign |
| Solar project Company 147, Clark County Solar |
82.3 MW | Agreement signed |
| Solar + storage project 309, Yellowstone County Solar + storage |
80.0 MW | In study |
| Solar + storage project 754, Box Elder County Solar + storage ยท Steel Solar, LLC |
80.0 MW | Agreement signed |
| Solar project 781, Tooele County Solar ยท Elektron Solar, LLC |
80.0 MW | Agreement signed |
| Halifax County Solar Solar |
80.0 MW | Agreement signed |
| Solar + storage project 784, Natrona County Solar + storage ยท Dinosolar, LLC |
80.0 MW | Agreement signed |
| Pitt Solar Solar |
80.0 MW | Agreement signed |
| Solar + storage project 792, Carbon County Solar + storage ยท RC Solar Energy LLC |
80.0 MW | Agreement signed |
| Springfield Solar Solar |
80.0 MW | Agreement signed |
| Solar project 292, Lake County Solar |
80.0 MW | Agreement signed |
| Hickory Wind Onshore wind |
78.7 MW | Paused / redesign |
| Edgecome Solar Energy Center Solar |
75.0 MW | Paused / redesign |
| Solar + storage project 789, Fremont County Solar + storage ยท Fresh Air Energy II, LLC |
74.9 MW | Agreement signed |
| Solar project 171, Gilchrist County Solar ยท Florida Renewable Partners, LLC |
74.5 MW | In study |
| Solar project 191, Manatee County Solar ยท FPL |
74.5 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)42 ยท 10.0 GW
- SPP (Southwest Power Pool)23 ยท 4,085 MW
- CAISO (California)13 ยท 3,530 MW
- PJM (Mid-Atlantic, Midwest)31 ยท 2,290 MW
- ERCOT (Texas)12 ยท 2,229 MW
- MISO (Midcontinent)15 ยท 1,433 MW
- Southeast (non-ISO utilities)11 ยท 977 MW
- ISO-NE (New England)2 ยท 866 MW
- NYISO (New York)13 ยท 370 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)