United States › Grid › Interconnection queues › Utah
SOLAR + STORAGE · WESTSolar + storage project 792, Carbon County
Solar + storage project 792, Carbon County is a 80.0 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Carbon County, Utah, connecting to PacifiCorp.
Queue statusConsented
- PlanningQueued Sep 2016 (completed)
- ConsentedMar 2019 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 792
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- RC Solar Energy LLC
- Connection point (POI)
- Mathington substation
- Location
- Carbon County, Utah
- Technology
- Solar: 80.0 MW · Battery
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed 3/7/19
- Queue status
- Active
- Entered queue
- 1 September 2016
- Agreement signed
- 7 March 2019
- Proposed online date
- December 2025
Location
Marker shows the centre of Carbon County; the queue data does not give exact sites.
Other requests in Carbon County
- Solar project 764, Carbon CountySolar · 80.0 MW · built
- Battery storage project C3-063, Carbon CountyBattery storage · 500 MW · withdrawn
- Battery storage project C2-16, Carbon CountyBattery storage · 300 MW · withdrawn
- Solar + storage project 1207, Carbon CountySolar + storage · 150 MW · withdrawn
- Solar + storage project C1-26, Carbon CountySolar + storage · 100 MW · withdrawn
- Onshore wind project 291, Carbon/Utah CountyOnshore wind · 100 MW · withdrawn
- Solar project 811, Carbon CountySolar · 100 MW · withdrawn
- Solar + storage project C3-058, Carbon CountySolar + storage · 100 MW · withdrawn
- Solar project 821, Carbon CountySolar · 87.0 MW · withdrawn
- Solar + storage project C3-123, Carbon CountySolar + storage · 85.0 MW · withdrawn
- Onshore wind project 867, Carbon CountyOnshore wind · 80.0 MW · withdrawn
- Solar project 1006, Carbon CountySolar · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem