United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR Β· WEST

Solar project 821, Carbon County

Solar project 821, Carbon County is a 87.0 MW solar request withdrawn in the West interconnection queue, in Carbon County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. ConsentedJan 2020 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
821
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Mathington substation
Location
Carbon County, Utah
Technology
Solar: 87.0 MW
Total requested
87.0 MW
Service type
Energy only (ERIS)
Study phase
IA executed 1/21/2020, Suspended 3/20/2020, IA terminated 3/13/23
Queue status
Withdrawn
Entered queue
15 November 2016
Agreement signed
21 January 2020
Proposed online date
February 2018
Withdrawn
March 2023

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Carbon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem