United States βΊ Grid βΊ Interconnection queues βΊ Utah
ONSHORE WIND Β· WESTOnshore wind project 291, Carbon/Utah County
Onshore wind project 291, Carbon/Utah County is a 100 MW onshore wind request withdrawn in the West interconnection queue, in Carbon/Utah County, Utah, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2009 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedJun 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 291
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Emery to Spanish Fork
- Location
- Carbon/Utah County, Utah
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA signed June 29, 2011
- Queue status
- Withdrawn
- Entered queue
- 25 September 2009
- Agreement signed
- 29 June 2011
- Proposed online date
- September 2013
Location
Marker shows the centre of Carbon/Utah County; the queue data does not give exact sites.
Other requests in Carbon/Utah County
- Solar + storage project 792, Carbon CountySolar + storage Β· 80.0 MW Β· agreement signed
- Solar project 764, Carbon CountySolar Β· 80.0 MW Β· built
- Battery storage project C3-063, Carbon CountyBattery storage Β· 500 MW Β· withdrawn
- Battery storage project C2-16, Carbon CountyBattery storage Β· 300 MW Β· withdrawn
- Solar + storage project 1207, Carbon CountySolar + storage Β· 150 MW Β· withdrawn
- Solar + storage project C1-26, Carbon CountySolar + storage Β· 100 MW Β· withdrawn
- Solar project 811, Carbon CountySolar Β· 100 MW Β· withdrawn
- Solar + storage project C3-058, Carbon CountySolar + storage Β· 100 MW Β· withdrawn
- Solar project 821, Carbon CountySolar Β· 87.0 MW Β· withdrawn
- Solar + storage project C3-123, Carbon CountySolar + storage Β· 85.0 MW Β· withdrawn
- Onshore wind project 867, Carbon CountyOnshore wind Β· 80.0 MW Β· withdrawn
- Solar project 1006, Carbon CountySolar Β· 60.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem