United States › Grid › Interconnection queues › Wyoming
SOLAR + STORAGE · WESTSolar + storage project 789, Fremont County
Solar + storage project 789, Fremont County is a 74.9 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Fremont County, Wyoming, connecting to PacifiCorp.
Queue statusConsented
- PlanningQueued Aug 2016 (completed)
- ConsentedOct 2020 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 789
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- Fresh Air Energy II, LLC
- Connection point (POI)
- Riverton-Thermopolis transmission line
- Location
- Fremont County, Wyoming
- Technology
- Solar: 74.9 MW · Battery
- Total requested
- 74.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA executed 10/8/20, suspended 6/17/21, unsuspended 8/4/2023
- Queue status
- Active
- Entered queue
- 8 August 2016
- Agreement signed
- 8 October 2020
- Proposed online date
- December 2026
Location
Marker shows the centre of Fremont County; the queue data does not give exact sites.
Other requests in Fremont County
- Gas project 646, Fremont CountyGas · 0.0 MW · built
- Onshore wind project 239, Fremont CountyOnshore wind · 250 MW · withdrawn
- Solar + storage project 951, Fremont CountySolar + storage · 80.0 MW · withdrawn
- Solar + storage project TCS-06, Fremont CountySolar + storage · 80.0 MW · withdrawn
- Solar project 875, Fremont CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem