United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

SOLAR + STORAGE Β· WEST

Solar + storage project TCS-06, Fremont County

Solar + storage project TCS-06, Fremont County is a 80.0 MW solar + storage request withdrawn in the West interconnection queue, in Fremont County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2017 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. ConsentedSep 2022 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
TCS-06
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Fresh Air Energy II, LLC
Connection point (POI)
Mustang - Spence transmission line
Location
Fremont County, Wyoming
Technology
Solar: 80.0 MW Β· Battery
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
LGIA executed 9/14/2022, LGIA terminated 5/3/2023
Queue status
Withdrawn
Entered queue
20 September 2017
Agreement signed
14 September 2022
Proposed online date
May 2027
Withdrawn
May 2023

Location

Marker shows the centre of Fremont County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Fremont County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem