United States › Grid › Interconnection queues › North Dakota
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in North Dakota — page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project GEN-2024-359, Stark County Battery storage |
100 MW | In study |
| Onshore wind project GEN-2017-215, Ward County Onshore wind |
100 MW | Agreement signed |
| Onshore wind project GEN-2017-214, Ward County Onshore wind |
100 MW | Agreement signed |
| Onshore wind project J3070, Morton County Onshore wind |
100 MW | In study |
| Onshore wind project J2097, Morton County Onshore wind |
100 MW | In study |
| Battery storage project J2913, Sargent County Battery storage |
90.0 MW | In study |
| Solar project J4077, Emmons County Solar |
45.0 MW | In study |
| Solar project J4070, Emmons County Solar |
40.0 MW | In study |
| Battery storage project GEN-2024-SR12, Lamoure County Battery storage |
20.0 MW | In study |
| Other project G150, Mcintosh County Other |
12.0 MW | In study |
| Onshore wind project GEN-2025-GR5, Ward County Onshore wind |
7.7 MW | In study |
| Gas project GI-1103, Burke County Gas · Blaise Energy |
0.8 MW | Agreement signed |
| Onshore wind project GEN-2025-GR3, Mclean County Onshore wind |
0.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- SPP (Southwest Power Pool)26 · 6,843 MW
- MISO (Midcontinent)31 · 6,519 MW
- West (non-ISO utilities)6 · 1,138 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)