United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in the USA — page 19

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 19 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 267, Saluda County
Solar
186 MWIn study Saluda, SCSoutheast Jun 2024target 2028
Solar project J4023, Clay County
Solar
185 MWIn study Clay, INMISO Feb 2025target 2029
Solar project J1944, Sanilac County
Solar
185 MWIn study Sanilac, MIMISO Aug 2021target 2023
Solar project J2237, Lee County
Solar
185 MWIn study Lee, ARMISO Dec 2021target 2027
Solar project J1518, Vermillion County
Solar
185 MWIn study Vermillion, INMISO Aug 2024target 2026
Solar project AH1-272, Van Buren County
Solar · Bankson Solar Project, LLC
185 MWIn study Van Buren, MIPJM Feb 2025target 2025
Solar project AH2-168, Madison County
Solar
185 MWIn study Madison, OHPJM Mar 2022target 2025
Solar project J1851, Morehouse Parish County
Solar
185 MWIn study Morehouse Parish, LAMISO Nov 2021target 2026
Solar project J3903, Mower County
Solar
185 MWIn study Mower, MNMISO Feb 2025target 2029
Maldives Solar (Oncor POI)
Solar
184 MWPaused / redesign Scurry, TXERCOT Dec 2022target 2026
Maldives Solar
Solar · Maldives Solar LLC
184 MWAgreement signed Scurry, TXERCOT Jul 2023target 2028
Leighton Solar SLF
Solar · Lavender Solar LLC
183 MWAgreement signed Limestone, TXERCOT May 2022target 2027
Solar project IC-1142, Baldwin County
Solar
183 MWAgreement signed Baldwin, GASoutheast May 2023target 2028
Solar project GEN-2021-108, Cass County
Solar
182 MWIn study Cass, NESPP May 20212025
Azalea Springs Solar
Solar · AZALEA SPRINGS SOLAR PARK LLC
181 MWAgreement signed Angelina, TXERCOT Jul 2017target 2025
Nightfall Solar
Solar · BDPU SOLAR NIGHTFALL, LLC
181 MWAgreement signed Uvalde, TXERCOT May 2019target 2026
Amphion Solar Phase 1
Solar · Amphion Solar, LLC
181 MWIn study Atascosa, TXERCOT Oct 2024target 2028
Alliance Solar
Solar
180 MWPaused / redesign Navarro, TXERCOT Jul 2023target 2028
Horseshoe Solar
Solar · Horseshoe Solar Energy LLC
180 MWIn study Livingston, NYNYISO May 2018target 2028
Solar project GEN-2023-205, Hughes County
Solar
180 MWIn study Hughes, OKSPP Oct 2023target 2028
Hoosier Line Solar
Solar
180 MWAgreement signed White, INPJM Sep 2019target 2027
Solar project J2737, Sabine Parish County
Solar
180 MWIn study Sabine Parish, LAMISO Sep 2025target 2026
Solar project J2656, Macon County
Solar
180 MWIn study Macon, ILMISO Sep 2022target 2026
Solar project J919, Jackson County
Solar
180 MWUnder construction Jackson, ARMISO Jun 20172023
Gateway Solar Energy Center
Solar · Gateway Solar Energy Center, LLC
180 MWIn study St. Lawrence, NYNYISO Mar 2017target 2028
Sculpin Solar
Solar
180 MWAgreement signed Dekalb, INPJM Aug 2019target 2028
Solar project GEN-2022-038, Harrison County
Solar
180 MWIn study Harrison, TXSPP Jun 2022target 2029
Solar project J1677, Macon County
Solar
180 MWIn study Macon, ILMISO Jun 2020target 2026
Solar project J3167, Fulton County
Solar
180 MWIn study Fulton, ILMISO Sep 2022target 2026
Solar project J2578, Tuscola County
Solar
180 MWIn study Tuscola, MIMISO Sep 2022target 2026
Cherry Solar
Solar
180 MWAgreement signed Northampton, NCPJM Oct 2016target 2025
Solar project AH1-338, Lee County
Solar · Prairie Brome Solar LLC
180 MWIn study Lee, ILPJM Feb 2025target 2025
Solar project J2847, Starke County
Solar
180 MWIn study Starke, INMISO Sep 2022target 2026
Bestla Solar
Solar
180 MWPaused / redesign Winkler, TXERCOT Jan 2017
Solar project IC-1225, Baldwin County
Solar
180 MWAgreement signed Baldwin, ALSoutheast Jan 2024target 2028
Solar project J1658, Hillsdale County
Solar
180 MWAgreement signed Hillsdale, MIMISO May 2025target 2025
Solar
Solar
180 MWIn study York, MEISO-NE Jul 2023target 2029
Scarlet Solar
Solar · Innovative Solar 416, LLC
180 MWIn study Castro, TXERCOT Dec 2019target 2025
Solar project J3342, Vermilion County
Solar
180 MWIn study Vermilion, ILMISO Apr 2024target 2028
Sloopy Solar Energy Center
Solar
180 MWAgreement signed Clark, OHPJM Mar 2019target 2028
Au Gres Solar Project
Solar · DTE Electric
180 MWIn study Arenac, MIMISO Aug 2025target 2028
Green Apple Solar
Solar
179 MWAgreement signed Androscoggin, MEISO-NE Feb 2021target 2027
Solar project AH1-537, Highland County
Solar · Riverlake Energy, LLC
179 MWIn study Highland, OHPJM Mar 2025target 2025
Millers Branch Solar II
Solar · Miller's Branch Solar, LLC
178 MWAgreement signed Haskell, TXERCOT Nov 2021target 2026
Solar project 387, Colbert County
Solar
178 MWAgreement signed Colbert, ALSoutheast Aug 2019target 2027
Solar project PIS056, Emery County
Solar · PacifiCorp
178 MWIn study Emery, UTWest May 2024target 2026
Solar project J4043, Eaton County
Solar
178 MWIn study Eaton, MIMISO Aug 2025target 2028
Solar project 823, Emery County
Solar · PacifiCorp Energy Supply Management
178 MWAgreement signed Emery, UTWest Nov 2016target 2027
Tri-County Solar
Solar
178 MWPaused / redesign Crane, TXERCOT Oct 2016
Hackberry Creek Solar
Solar · Hackberry Creek Solar LLC
176 MWAgreement signed Mitchell, TXERCOT Jul 2023target 2028
Page 19 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)