Solar project J4043, Eaton County

Solar project J4043, Eaton County is a 178 MW solar request in interconnection study in the MISO interconnection queue, in Eaton County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4043
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Oneida
Location
Eaton County, Michigan
Technology
Solar: 178 MW
Total requested
178 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
13 August 2025
Proposed online date
April 2028

Location

Marker shows the centre of Eaton County; the queue data does not give exact sites.