United States › Grid › Interconnection queues › Michigan

BATTERY STORAGE · MISO

Battery storage project J3836, Eaton County

Battery storage project J3836, Eaton County is a 250 MW battery storage request in interconnection study in the MISO interconnection queue, in Eaton County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3836
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
ONEIDA
Location
Eaton County, Michigan
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
24 October 2024
Proposed online date
October 2028

Location

Marker shows the centre of Eaton County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Eaton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem