Solar project J1192, Eaton County

Solar project J1192, Eaton County is a 35.0 MW solar request withdrawn in the MISO interconnection queue, in Eaton County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandonedOct 2022 (project stopped here)
  3. ConsentedAug 2022 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1192
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Oneida 138kV Substation
Location
Eaton County, Michigan
Technology
Solar: 35.0 MW
Total requested
35.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Withdrawn
Queue status
Withdrawn
Entered queue
25 March 2019
Agreement signed
17 August 2022
Proposed online date
July 2024
Withdrawn
October 2022

Location

Marker shows the centre of Eaton County; the queue data does not give exact sites.