United States › Grid › Interconnection queues › Michigan
SOLAR · MISOAu Gres Solar Project
Au Gres Solar Project is a 180 MW solar request in interconnection study in the MISO interconnection queue, in Arenac County, Michigan, connecting to DTE Electric.
Queue statusIn planning
- PlanningQueued Aug 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- E0007
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DTE Electric
- Developer
- DTE Electric
- Connection point (POI)
- Twining-Whittemore 138kV
- Location
- Arenac County, Michigan
- Technology
- Solar: 180 MW
- Total requested
- 180 MW
- Service type
- Network resource (NRIS)
- Study phase
- Request Status: Active; Post GIA Status: Not started
- Queue status
- Active
- Entered queue
- 6 August 2025
- Proposed online date
- April 2028
Location
Marker shows the centre of Arenac County; the queue data does not give exact sites.
Other requests in Arenac County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem