United States › Grid › Interconnection queues › Georgia

SOLAR · SOUTHEAST

Solar project IC-1142, Baldwin County

Solar project IC-1142, Baldwin County is a 183 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Baldwin County, Georgia, connecting to Southern Company.

Queue statusConsented
  1. PlanningQueued May 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
IC-1142
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Gordon - Milledgeville (White) 115 kV Line
Location
Baldwin County, Georgia
Technology
Solar: 183 MW
Total requested
183 MW
Service type
Network resource (NRIS)
Study phase
GIA Executed; NTP Pending
Queue status
Active
Entered queue
30 May 2023
Proposed online date
May 2028

Location

Marker shows the centre of Baldwin County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Baldwin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem