Solar project GEN-2022-038, Harrison County

Solar project GEN-2022-038, Harrison County is a 180 MW solar request in interconnection study in the SPP interconnection queue, in Harrison County, Texas, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Jun 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2022-038
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Longwood to Scottville 138 kV line
Location
Harrison County, Texas
Technology
Solar: 180 MW
Total requested
180 MW
Service type
Energy only (ERIS)
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
23 June 2022
Proposed online date
April 2029

Location

Marker shows the centre of Harrison County; the queue data does not give exact sites.