SOLAR + STORAGE · SPP

Solar + storage project GEN-2023-193, Harrison County

Solar + storage project GEN-2023-193, Harrison County is a 175 MW solar + storage request in interconnection study in the SPP interconnection queue, in Harrison County, Texas, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2023-193
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Pirkey - Whitney 138 kV Line
Location
Harrison County, Texas
Technology
Solar: 175 MW · Battery
Total requested
175 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
2 October 2023
Proposed online date
March 2028

Location

Marker shows the centre of Harrison County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Harrison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem