Gas project GEN-2022-GR1, Harrison County

Gas project GEN-2022-GR1, Harrison County is a 513 MW gas request with a signed interconnection agreement in the SPP interconnection queue, in Harrison County, Texas, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Mar 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2022-GR1
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Pirkey 138 kV
Location
Harrison County, Texas
Technology
Gas: 513 MW
Total requested
513 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
23 March 2022
Proposed online date
December 2027

Location

Marker shows the centre of Harrison County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Harrison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem