United States › Grid › Interconnection queues › Louisiana

SOLAR · MISO

Solar project J1851, Morehouse Parish County

Solar project J1851, Morehouse Parish County is a 185 MW solar request in interconnection study in the MISO interconnection queue, in Morehouse Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusIn planning
  1. PlanningQueued Nov 2021 (current stage)
  2. ConsentedOct 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1851
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
CROSSETT NORTH - BEEKMAN 115.0kV
Location
Morehouse Parish County, Louisiana
Technology
Solar: 185 MW
Total requested
185 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
30 November 2021
Agreement signed
14 October 2025
Proposed online date
November 2026

Location

Marker shows the centre of Morehouse Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Morehouse Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem