United States › Grid › Interconnection queues › Louisiana
SOLAR + STORAGE · MISOSolar + storage project J3118, Morehouse Parish County
Solar + storage project J3118, Morehouse Parish County is a 160 MW solar + storage request in interconnection study in the MISO interconnection queue, in Morehouse Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3118
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Taping the 'Galion / 3GALION (337444)' to 'Oak Grove / 3OAK_GROVE! (337445)' 115kV line
- Location
- Morehouse Parish County, Louisiana
- Technology
- Solar: 160 MW · Battery
- Total requested
- 160 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- June 2026
Location
Marker shows the centre of Morehouse Parish County; the queue data does not give exact sites.
Other requests in Morehouse Parish County
- Solar project J1827, Morehouse Parish CountySolar · 90.0 MW · agreement signed
- Solar project J3454, Morehouse Parish CountySolar · 300 MW · in study
- Solar project J2371, Morehouse Parish CountySolar · 250 MW · in study
- Solar project J3601, Morehouse Parish CountySolar · 200 MW · in study
- Solar project J1851, Morehouse Parish CountySolar · 185 MW · in study
- Onshore wind project J2965, Morehouse Parish CountyOnshore wind · 180 MW · in study
- Solar + storage project J2956, Morehouse Parish CountySolar + storage · 100 MW · in study
- Solar project J3988, Morehouse Parish CountySolar · 85.0 MW · in study
- Solar project J697, Morehouse Parish CountySolar · 150 MW · built
- Solar project J1436, Morehouse Parish CountySolar · 50.0 MW · built
- Gas project J4141, Morehouse Parish CountyGas · 650 MW · withdrawn
- Solar project J2706, Morehouse Parish CountySolar · 500 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem