SOLAR + STORAGE · MISO

Solar + storage project J3118, Morehouse Parish County

Solar + storage project J3118, Morehouse Parish County is a 160 MW solar + storage request in interconnection study in the MISO interconnection queue, in Morehouse Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3118
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Taping the 'Galion / 3GALION (337444)' to 'Oak Grove / 3OAK_GROVE! (337445)' 115kV line
Location
Morehouse Parish County, Louisiana
Technology
Solar: 160 MW · Battery
Total requested
160 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
15 September 2022
Proposed online date
June 2026

Location

Marker shows the centre of Morehouse Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Morehouse Parish County