United States › Grid › Interconnection queues › Minnesota

SOLAR · MISO

Solar project J3903, Mower County

Solar project J3903, Mower County is a 185 MW solar request in interconnection study in the MISO interconnection queue, in Mower County, Minnesota, connecting to SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3903
Grid region
MISO (Midcontinent)
Utility / transmission owner
SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY
Connection point (POI)
North Austin - Adams (ITC) 161.0kV
Location
Mower County, Minnesota
Technology
Solar: 185 MW
Total requested
185 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
19 February 2025
Proposed online date
March 2029

Location

Marker shows the centre of Mower County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Mower County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem