United States › Grid › Interconnection queues › Minnesota
SOLAR · MISOSolar project J523, Mower County
Solar project J523, Mower County is a 50.0 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Mower County, Minnesota.
Queue statusConsented
- PlanningQueued Nov 2015 (completed)
- ConsentedMar 2019 (current stage)
- Construction (not yet reached)
- OperatingDec 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J523
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- ITCM Adams 161 kV Substation
- Location
- Mower County, Minnesota
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- GIA
- Queue status
- Active
- Entered queue
- 16 November 2015
- Agreement signed
- 7 March 2019
- Proposed online date
- September 2021
- Came online
- December 2024
Location
Marker shows the centre of Mower County; the queue data does not give exact sites.
Other requests in Mower County
- Onshore wind project J967, Mower CountyOnshore wind · 150 MW · under construction
- Solar project J1072, Mower CountySolar · 150 MW · under construction
- Battery storage project J4078, Mower CountyBattery storage · 500 MW · in study
- Solar project J3903, Mower CountySolar · 185 MW · in study
- Solar project J2861, Mower CountySolar · 147 MW · in study
- Solar project J4057, Mower CountySolar · 127 MW · in study
- Onshore wind project G172, Mower CountyOnshore wind · 300 MW · built
- Onshore wind project G113, Mower CountyOnshore wind · 200 MW · built
- Onshore wind project J278, Mower CountyOnshore wind · 200 MW · built
- Onshore wind project G362, Mower CountyOnshore wind · 200 MW · built
- Onshore wind project G330, Mower CountyOnshore wind · 19.0 MW · built
- Gas project J3549, Mower CountyGas · 515 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem