Solar project J4057, Mower County is a 127 MW solar request in interconnection study in the MISO interconnection queue, in Mower County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
Queue statusIn planning
- PlanningQueued Aug 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4057
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- YANKEE
- Location
- Mower County, Minnesota
- Technology
- Solar: 127 MW
- Total requested
- 127 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 22 August 2025
- Proposed online date
- May 2030
Location
Marker shows the centre of Mower County; the queue data does not give exact sites.
Other requests in Mower County
- Onshore wind project J967, Mower CountyOnshore wind · 150 MW · under construction
- Solar project J1072, Mower CountySolar · 150 MW · under construction
- Solar project J523, Mower CountySolar · 50.0 MW · agreement signed
- Battery storage project J4078, Mower CountyBattery storage · 500 MW · in study
- Solar project J3903, Mower CountySolar · 185 MW · in study
- Solar project J2861, Mower CountySolar · 147 MW · in study
- Onshore wind project G172, Mower CountyOnshore wind · 300 MW · built
- Onshore wind project G113, Mower CountyOnshore wind · 200 MW · built
- Onshore wind project J278, Mower CountyOnshore wind · 200 MW · built
- Onshore wind project G362, Mower CountyOnshore wind · 200 MW · built
- Onshore wind project G330, Mower CountyOnshore wind · 19.0 MW · built
- Gas project J3549, Mower CountyGas · 515 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem