United States › Grid › Interconnection queues › Minnesota
SOLAR · MISOSolar project J1072, Mower County
Solar project J1072, Mower County is a 150 MW solar request under construction in the MISO interconnection queue, in Mower County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedJun 2021 (completed)
- Construction (current stage)
- OperatingTarget Aug 2023 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1072
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- Adams 345 kV Substation
- Location
- Mower County, Minnesota
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 15 June 2021
- Proposed online date
- August 2023
Location
Marker shows the centre of Mower County; the queue data does not give exact sites.
Other requests in Mower County
- Onshore wind project J967, Mower CountyOnshore wind · 150 MW · under construction
- Solar project J523, Mower CountySolar · 50.0 MW · agreement signed
- Battery storage project J4078, Mower CountyBattery storage · 500 MW · in study
- Solar project J3903, Mower CountySolar · 185 MW · in study
- Solar project J2861, Mower CountySolar · 147 MW · in study
- Solar project J4057, Mower CountySolar · 127 MW · in study
- Onshore wind project G172, Mower CountyOnshore wind · 300 MW · built
- Onshore wind project G113, Mower CountyOnshore wind · 200 MW · built
- Onshore wind project J278, Mower CountyOnshore wind · 200 MW · built
- Onshore wind project G362, Mower CountyOnshore wind · 200 MW · built
- Onshore wind project G330, Mower CountyOnshore wind · 19.0 MW · built
- Gas project J3549, Mower CountyGas · 515 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem