ONSHORE WIND · MISO

Onshore wind project J278, Mower County

Onshore wind project J278, Mower County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Mower County, Minnesota.

Queue statusOperating
  1. PlanningQueued Mar 2013 (completed)
  2. ConsentedJul 2014 (completed)
  3. Construction (completed)
  4. OperatingSep 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J278
Grid region
MISO (Midcontinent)
Connection point (POI)
161 kV bus at the Pleasant Valley Station
Location
Mower County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
18 March 2013
Agreement signed
17 July 2014
Proposed online date
September 2014
Came online
September 2014

Location

Marker shows the centre of Mower County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Mower County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem