🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project G330, Mower County

Onshore wind project G330, Mower County is a 19.0 MW onshore wind request built and operating in the MISO interconnection queue, in Mower County, Minnesota.

Queue statusOperating
  1. PlanningQueued Apr 2003 (completed)
  2. ConsentedDec 2003 (completed)
  3. Construction (completed)
  4. OperatingDec 2003 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G330
Grid region
MISO (Midcontinent)
Connection point (POI)
Adams - St. Angsgar 69kV
Location
Mower County, Minnesota
Technology
Wind: 19.0 MW
Total requested
19.0 MW
Study phase
SPA - SIS
Queue status
Operational
Entered queue
11 April 2003
Agreement signed
19 December 2003
Proposed online date
December 2003
Came online
December 2003

Location

Marker shows the centre of Mower County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Mower County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem