United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

GAS Β· MISO

Gas project J3549, Mower County

Gas project J3549, Mower County is a 515 MW gas request withdrawn in the MISO interconnection queue, in Mower County, Minnesota, connecting to GREAT RIVER ENERGY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3549
Grid region
MISO (Midcontinent)
Utility / transmission owner
GREAT RIVER ENERGY
Connection point (POI)
NOT IN DROPDOWN MENU
Location
Mower County, Minnesota
Technology
Gas: 515 MW
Total requested
515 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
17 April 2024
Proposed online date
June 2026
Withdrawn
December 2025

Location

Marker shows the centre of Mower County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Mower County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem