NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown2,255782.1 GW in total
In planning1,590scoping or awaiting consent
Consented or building265closest to connecting
Built400connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

2,255 projects · page 36 of 46
ProjectCapacityStageConnection siteFrom
Whitegate Tertiary Connection
Battery storage · HD144WHI LTD
57 MWBuilt Whitegate 275kV Substation
National Grid (England & Wales)
Whitelaw Brae Windfarm
Onshore wind · Whitelaw Brae Windfarm Limited
57 MWUnder Construction/Commissioning Whitelaw Brae 'A' and 'B' 33kV Substations
SP Transmission (south Scotland)
Jul 2026
Willington
Battery storage · Pivoted Power LLP
57 MWScoping Willington East 400kV Substation
National Grid (England & Wales)
Jun 2026
Wymondley
Solar + storage · Priory Generation Limited
57 MWConsents Approved Wymondley 400kV Substation
National Grid (England & Wales)
May 2027
GH DEVCO Gretna Green BESS
Battery storage · Gretna Energy Storage Limited
56 MWScoping Gresham House Gretna 400/132kv Substation
SP Transmission (south Scotland)
Oct 2032
Harestanes West Wind Farm
Onshore wind · Scottish Power Renewables (UK) Limited
56 MWScoping Harestanes West Wind Farm 132/33kV
SP Transmission (south Scotland)
Sep 2029
Manquhill Wind Farm
Wind + storage · Energyfarm UK Manquhill Ltd
56 MWScoping Manquhill Wind Farm 132/33kV Substation
SP Transmission (south Scotland)
Oct 2036
Galawhistle Wind Farm
Onshore wind · Galawhistle Wind Farm Limited
55 MWBuilt Galawhistle 132/33kV Substation
SP Transmission (south Scotland)
AGS Nerston 2 BESS
Battery storage · Advance Grid Solutions Limited
55 MWScoping East Kilbride B 275/33kV Substation
SP Transmission (south Scotland)
Oct 2033
AGS Nerston 3 BESS
Battery storage · Advance Grid Solutions Limited
55 MWScoping East Kilbride B 275/33kV Substation
SP Transmission (south Scotland)
Oct 2033
Drinkstone Hybrid
Solar + storage · Buccleuch Estates, Ltd. (The)
55 MWScoping Drinkstone Hybrid 132/33kV substation
SP Transmission (south Scotland)
Jul 2035
Indaver Rivenhall IWMF
Other · Indaver Rivenhall Limited
55 MWBuilt Braintree GSP
National Grid (England & Wales)
Markinch (Rothes) Biomass CHP Plant
Other · Rwe Markinch Limited
55 MWBuilt Glenrothes GSP
SP Transmission (south Scotland)
Rogerton Cottage BESS
Battery storage · Drax BESS Ek Limited
55 MWScoping East Kilbride 275/33kV GSP
SP Transmission (south Scotland)
Mar 2027
Hagshaw Hill Phase 2
Onshore wind · Hagshaw Hill Repowering Ltd
54 MWBuilt Hagshaw Hill Wind Farm 33kV Substation
SP Transmission (south Scotland)
Lees Hill Renewable Energy Park
Solar + storage · Fred Olsen Renewables Limited
54 MWScoping Kelloe Mains 400kV Substation
SP Transmission (south Scotland)
Apr 2033
Sclenteuch Energy Park
Wind + storage · Sclenteuch Energy Limited
54 MWScoping Sclenteuch Energy Park 132kV
SP Transmission (south Scotland)
Oct 2029
Ditcher Law
Wind + storage · E Power Limited
53 MWAwaiting Consents Dunlaw Extension 132/33kV
SP Transmission (south Scotland)
Oct 2031
Mark Hill Wind Farm
Onshore wind · Scottish Power Renewables (UK) Limited
53 MWBuilt Mark Hill 275/132kV
SP Transmission (south Scotland)
Blackcraig Wind Farm
Onshore wind · Blackcraig Wind Farm (Scotland) Limited
53 MWBuilt Blackcraig 132/33kV
SP Transmission (south Scotland)
High Brenfield 1
Onshore wind · High Brenfield Wind Farm Limited
53 MWScoping Craig Murrail 275/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2034
Watten Wind Farm
Onshore wind · Edf Energy Renewables Limited
53 MWScoping Mybster 3 132/33kV Substation
SSEN Transmission (north Scotland)
Jun 2028
Baillie Wind Farm
Onshore wind · Baillie Windfarm Limited
53 MWBuilt Dounreay GSP
SSEN Transmission (north Scotland)
Harburnhead Wind Farm
Onshore wind · Ldv Harburnhead Limited
52 MWBuilt Livingston East 132/33kV
SP Transmission (south Scotland)
Lochay (Part of Killin Cascade Hydro Scheme)
Hydro and pumped storage · Sse Generation Limited
51 MWUnder Construction/Commissioning Lochay 132/11kV Substation
SSEN Transmission (north Scotland)
Jan 2027
Kaimes Energy Park
Battery storage · HP Trotter t/a Printonan Farm
51 MWScoping Kaimes GSP
SP Transmission (south Scotland)
Apr 2027
Middle Muir Wind Farm
Onshore wind · OnPath Energy Limited (MIDDLE MUIR WIND FARM) LIMITED
51 MWBuilt Middlemuir 132/33kV
SP Transmission (south Scotland)
50MW BESS Connagill
Battery storage · Cerulisia Ltd
50 MWScoping New Connagill 275/132kV Substation
SSEN Transmission (north Scotland)
Oct 2031
Afton Wind Farm
Onshore wind · Afton Wind Farm Limited
50 MWBuilt Blackhill 132/33kV
SP Transmission (south Scotland)
AGS Nerston BESS
Battery storage · Advance Grid Solutions Limited
50 MWScoping East Kilbride B 275/33kV Substation
SP Transmission (south Scotland)
Oct 2033
Allt an Tuir Renewable Energy Park
Solar + storage · Allt An Tuir Renewable Energy Park Limited
50 MWScoping Shin 1 GSP
SSEN Transmission (north Scotland)
Jun 2031
Almondell Lodge BESS & Solar Development
Battery storage · Broxburn Energy Storage Limited
50 MWBuilt Broxburn 132/33kV
SP Transmission (south Scotland)
Aultcraggie BESS
Battery storage · Opde UK Limited
50 MWScoping Brora GSP
SSEN Transmission (north Scotland)
Oct 2034
Beechgreen Energyfarm
Solar · Beechgreen Energyfarm Limited
50 MWBuilt Burwell Main 400kV Substation
National Grid (England & Wales)
Beinn an Tuirc 3
Onshore wind · Scottish Power Renewables (UK) Limited
50 MWBuilt Carradale 1 GSP
SSEN Transmission (north Scotland)
Bicker Fen 2 Solar
Solar + storage · Agr Solar 3 Limited
50 MWAwaiting Consents Bicker Fen 400kV Substation
National Grid (England & Wales)
Jul 2026
Blackbraes PV+BESS
Solar + storage · Chint Solar UK Management Ltd
50 MWScoping Blackbraes IDNO GSP
SP Transmission (south Scotland)
Oct 2031
Bramley BESS
Battery storage · Bramley BESS Limited
50 MWUnder Construction/Commissioning Bramley 400kV Substation
National Grid (England & Wales)
Oct 2027
Breakish Windfarm
Onshore wind · Asuk Holdco 2 Limited
50 MWScoping Breakish 132kV Substation
SSEN Transmission (north Scotland)
May 2029
Cloud Hill Windfarm
Wind + storage · Cloud Hill Windfarm Limited
50 MWAwaiting Consents Glenglass 132/33kV
SP Transmission (south Scotland)
May 2030
Coldstream BESS
Battery storage · Igp Energy Storage 4 Limited
50 MWScoping Eccles 400/132kV
SP Transmission (south Scotland)
Oct 2030
Cornharrow Wind Farm
Onshore wind · Energyfarm UK Cornharrow LLP
50 MWScoping Quantans Hill 132kV Substation
SP Transmission (south Scotland)
Oct 2030
Coylton 275kV Greener Grid Park
Battery storage · Coylton Energy Limited
50 MWConsents Approved Coylton 275kV substation
SP Transmission (south Scotland)
May 2026
Cumberhead
Onshore wind · Cumberhead Wind Energy Limited
50 MWBuilt Cumberhead 33kV
SP Transmission (south Scotland)
Cwm Rheidol
Hydro and pumped storage · Statkraft Energy Ltd.
50 MWBuilt Cwm Rheidol
National Grid (England & Wales)
Elvanfoot (50MW) Energy Storage
Battery storage · Elvanfoot Energy Storage 2 Limited
50 MWScoping Elvanfoot Energy Storage 132/33Kv Collector Substation
SP Transmission (south Scotland)
Oct 2029
ER BBR Energy
Solar + storage · Er Project Development Co Limited
50 MWScoping Er Bbr Energy 132kV Substation
SP Transmission (south Scotland)
Oct 2029
Fell Wind Farm
Onshore wind · Energyfarm UK Fell LLP
50 MWScoping SPT Margree collector substation
SP Transmission (south Scotland)
Oct 2029
Garlogie B-1
Solar + storage · Garlogie Energy Centre Limited
50 MWScoping Garlogie Production B 275/33kV GSP
SSEN Transmission (north Scotland)
Oct 2033
Garlogie B-2
Solar + storage · Garlogie Energy Centre Limited
50 MWScoping Garlogie Production B 275/33kV GSP
SSEN Transmission (north Scotland)
Oct 2033
Page 36 of 46

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.