Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · SPTWhitelaw Brae Windfarm
Whitelaw Brae Windfarm is a 57 MW onshore wind project under construction or commissioning, connecting to the SP Transmission (south Scotland) network at Whitelaw Brae 'A' and 'B' 33kV Substations, with capacity due from July 2026. The connection agreement is held by Whitelaw Brae Windfarm Limited.
Project stageUnder construction
- Planning (completed)
- Consented (completed)
- Construction (current stage)
- OperatingFrom Jul 2026 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-000341
- Customer
- Whitelaw Brae Windfarm Limited
- Technology
- Wind Onshore
- Total capacity
- 57 MW
- Change in this agreement
- +57 MW
- Capacity effective from
- 31 July 2026
- Connection site
- Whitelaw Brae 'A' and 'B' 33kV Substations
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Under Construction/Commissioning
- Connections reform gate
- Gate 2
Connection site
The connection site could not be placed on the map.
Projects connecting near Whitelaw Brae 'A' and 'B' · Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem