Grid infrastructure β€Ί Connection queue β€Ί Battery storage

BATTERY STORAGE Β· NGET

Willington

Willington is a 57 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at Willington East 400kV Substation, with capacity due from June 2026. The connection agreement is held by Pivoted Power LLP.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-000326
Customer
Pivoted Power LLP
Technology
Energy Storage System
Total capacity
57 MW
Change in this agreement
+57 MW
Capacity effective from
30 June 2026
Connection site
Willington East 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Willington East Β· Grid map

Other projects at Willington East 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem