Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · SPT

AGS Nerston 2 BESS

AGS Nerston 2 BESS is a 55 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at East Kilbride B 275/33kV Substation, with capacity due from October 2033. The connection agreement is held by Advance Grid Solutions Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004226
Customer
Advance Grid Solutions Limited
Technology
Energy Storage System
Total capacity
55 MW
Change in this agreement
+55 MW
Capacity effective from
31 October 2033
Connection site
East Kilbride B 275/33kV Substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near East Kilbride B · Grid map

Other projects at East Kilbride B 275/33kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem