Grid infrastructure › Connection queue › Hydro and pumped storage
HYDRO AND PUMPED STORAGE · SHETLochay (Part of Killin Cascade Hydro Scheme)
Lochay (Part of Killin Cascade Hydro Scheme) is a 51 MW hydro and pumped storage project under construction or commissioning, connecting to the SSEN Transmission (north Scotland) network at Lochay 132/11kV Substation, with capacity due from January 2027. The connection agreement is held by Sse Generation Limited.
Project stageUnder construction
- Planning (completed)
- Consented (completed)
- Construction (current stage)
- OperatingFrom Jan 2027 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-000174-2
- Customer
- Sse Generation Limited
- Technology
- Hydro
- Total capacity
- 51 MW
- Change in this agreement
- +6.2 MW
- Capacity effective from
- 1 January 2027
- Connection site
- Lochay 132/11kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Under Construction/Commissioning
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Lochay 132/11kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem