United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown16528.2 GW
Active in queue10.3 GW61 requests
Agreement signed3,007 MW20 requests
Withdrawn16528.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

165 requests Β· page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J1130, Warren County
Gas
1,110 MWWithdrawn / abandoned Warren, MSMISO Mar 2018target 2023
Onshore wind project J957, Mercer County
Onshore wind
800 MWWithdrawn / abandoned Mercer, MOMISO Mar 2018target 2010
Onshore wind project J1004, Mecosta County
Onshore wind
800 MWWithdrawn / abandoned Mecosta, MIMISO Mar 2018target 2020
Gas project J1119, Jackson County
Gas
600 MWWithdrawn / abandoned Jackson, MIMISO Mar 2018target 2021
Solar project J1097, Lonoke County
Solar
500 MWWithdrawn / abandoned Lonoke, ARMISO Mar 2018target 2021
Onshore wind project J1106, Redwood County
Onshore wind
414 MWWithdrawn / abandoned Redwood, MNMISO Mar 2018target 2021
Solar project J1010, Kenosha County
Solar
400 MWWithdrawn / abandoned Kenosha, WIMISO Mar 2018target 2020
Solar project J1009, Kenosha County
Solar
400 MWWithdrawn / abandoned Kenosha, WIMISO Mar 2018target 2020
Onshore wind project J960, Presque Isle County
Onshore wind
400 MWWithdrawn / abandoned Presque Isle, MIMISO Mar 2018target 2020
Solar project J1011, Kenosha County
Solar
400 MWWithdrawn / abandoned Kenosha, WIMISO Mar 2018target 2022
Onshore wind project J966, Putnam County
Onshore wind
400 MWWithdrawn / abandoned Putnam, MOMISO Mar 2018target 2020
Onshore wind project J1082, Grundy County
Onshore wind
400 MWWithdrawn / abandoned Grundy, MOMISO Mar 2018target 2020
Onshore wind project J1043, Montcalm County
Onshore wind
374 MWWithdrawn / abandoned Montcalm, MIMISO Mar 2018target 2024
Onshore wind project J1075, Cass County
Onshore wind
350 MWWithdrawn / abandoned Cass, MIMISO Mar 2018target 2020
Solar project J1095, Desoto County
Solar
300 MWWithdrawn / abandoned Desoto, MSMISO Mar 2018target 2021
Onshore wind project J1085, Marathon County
Onshore wind
300 MWWithdrawn / abandoned Marathon, WIMISO Mar 2018target 2021
Solar project J1073, Iberville Parish County
Solar
300 MWWithdrawn / abandoned Iberville Parish, LAMISO Mar 2018target 2021
Solar project J1053, Jefferson County
Solar
300 MWWithdrawn / abandoned Jefferson, WIMISO Mar 2018target 2021
Onshore wind project J1081, Polk County
Onshore wind
300 MWWithdrawn / abandoned Polk, MNMISO Mar 2018target 2020
Onshore wind project J977, Jackson County
Onshore wind
300 MWWithdrawn / abandoned Jackson, MNMISO Mar 2018target 2021
Onshore wind project J1177, Schuyler County
Onshore wind
300 MWWithdrawn / abandoned Schuyler, MOMISO Mar 2018target 2020
Solar project J1078, Mississippi County
Solar
300 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2018target 2021
Solar project J1179, Chisago County
Solar
300 MWWithdrawn / abandoned Chisago, MNMISO Mar 2018target 2021
Solar project J1059, Cape Girardeau County
Solar
300 MWWithdrawn / abandoned Cape Girardeau, MOMISO Mar 2018target 2021
Solar project J1061, Wabasha County
Solar
300 MWWithdrawn / abandoned Wabasha, MNMISO Mar 2018target 2021
Gas project J1151, Ascension Parish County
Gas
252 MWWithdrawn / abandoned Ascension Parish, LAMISO Mar 2018target 2020
Onshore wind project J971, Nobles County
Onshore wind
250 MWWithdrawn / abandoned Nobles, MNMISO Mar 2018target 2020
Onshore wind project J974, Fulton County
Onshore wind
250 MWWithdrawn / abandoned Fulton, ILMISO Mar 2018target 2023
Onshore wind project J973, Coles County
Onshore wind
250 MWWithdrawn / abandoned Coles, ILMISO Mar 2018target 2020
Onshore wind project J1048, Mecosta County
Onshore wind
250 MWWithdrawn / abandoned Mecosta, MIMISO Mar 2018target 2020
Onshore wind project J1077, Cass County
Onshore wind
250 MWWithdrawn / abandoned Cass, MIMISO Mar 2018target 2020
Solar project J1020, Jasper County
Solar
250 MWWithdrawn / abandoned Jasper, MSMISO Mar 2018target 2022
Solar project J1049, Forrest County
Solar
250 MWWithdrawn / abandoned Forrest, MSMISO Mar 2018target 2022
Onshore wind project J1109, Cass County
Onshore wind
207 MWWithdrawn / abandoned Cass, NDMISO Mar 2018target 2021
Onshore wind project J1024, Nodaway County
Onshore wind
200 MWWithdrawn / abandoned Nodaway, MOMISO Mar 2018target 2022
Solar project J1029, East Feliciana Parish County
Solar
200 MWWithdrawn / abandoned East Feliciana Parish, LAMISO Mar 2018target 2020
Solar project J988, Wayne County
Solar
200 MWWithdrawn / abandoned Wayne, MSMISO Mar 2018target 2022
Solar project J1152, Hancock County
Solar
200 MWWithdrawn / abandoned Hancock, INMISO Mar 2018target 2021
Solar project J1149, Yellow Medicine County
Solar
200 MWWithdrawn / abandoned Yellow Medicine, MNMISO Mar 2018target 2021
Solar project J997, Lamoure County
Solar
200 MWWithdrawn / abandoned Lamoure, NDMISO Mar 2018target 2020
Onshore wind project J1021, Piatt County
Onshore wind
200 MWWithdrawn / abandoned Piatt, ILMISO Mar 2018target 2021
Onshore wind project J1114, Plymouth County
Onshore wind
200 MWWithdrawn / abandoned Plymouth, IAMISO Mar 2018target 2021
Onshore wind project J1065, Gratiot County
Onshore wind
200 MWWithdrawn / abandoned Gratiot, MIMISO Mar 2018target 2020
Solar project J1099, Iberville Parish County
Solar
200 MWWithdrawn / abandoned Iberville Parish, LAMISO Mar 2018target 2021
Onshore wind project J980, Christian County
Onshore wind
200 MWWithdrawn / abandoned Christian, ILMISO Mar 2018target 2021
Solar project J1170, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Mar 2018target 2021
Solar project J1105, Dakota County
Solar
200 MWWithdrawn / abandoned Dakota, MNMISO Mar 2018target 2020
Onshore wind project J981, Washington County
Onshore wind
200 MWWithdrawn / abandoned Washington, IAMISO Mar 2018target 2021
Solar project J1044, Walworth County
Solar
200 MWWithdrawn / abandoned Walworth, WIMISO Mar 2018target 2022
Solar project J991, Clay County
Solar
200 MWWithdrawn / abandoned Clay, ILMISO Mar 2018target 2023
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)