United States βΊ Grid βΊ Interconnection queues βΊ Illinois
SOLAR Β· MISOSolar project J991, Clay County
Solar project J991, Clay County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Clay County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- ConsentedOct 2021 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J991
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Xenia 345kV Switching Station
- Location
- Clay County, Illinois
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 12 March 2018
- Agreement signed
- 12 October 2021
- Proposed online date
- October 2023
- Withdrawn
- December 2025
Location
Marker shows the centre of Clay County; the queue data does not give exact sites.
Other requests in Clay County
- Solar project J813, Clay CountySolar Β· 275 MW Β· under construction
- Solar project J3880, Clay CountySolar Β· 200 MW Β· in study
- Solar project J3811, Clay CountySolar Β· 200 MW Β· in study
- Battery storage project J3881, Clay CountyBattery storage Β· 200 MW Β· in study
- Battery storage project J2379, Clay CountyBattery storage Β· 200 MW Β· in study
- Solar project J2033, Clay CountySolar Β· 200 MW Β· in study
- Solar project J1679, Clay CountySolar Β· 125 MW Β· in study
- Battery storage project J2197, Clay CountyBattery storage Β· 100 MW Β· in study
- Solar project J3389, Clay CountySolar Β· 150 MW Β· withdrawn
- Solar project J2125, Clay CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem