πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J1114, Plymouth County

Onshore wind project J1114, Plymouth County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Plymouth County, Iowa, connecting to MIDAMERICAN ENERGY COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1114
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY COMPANY
Connection point (POI)
J506 Substation on Raun - Highland 345 kV Line
Location
Plymouth County, Iowa
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
September 2021
Withdrawn
March 2020

Location

Marker shows the centre of Plymouth County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Plymouth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem