United States › Grid › Interconnection queues › Iowa

ONSHORE WIND · MISO

Onshore wind project J748, Plymouth County

Onshore wind project J748, Plymouth County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Plymouth County, Iowa, connecting to MIDAMERICAN ENERGY COMPANY.

Queue statusOperating
  1. PlanningQueued Nov 2016 (completed)
  2. ConsentedMar 2020 (completed)
  3. Construction (completed)
  4. OperatingOct 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J748
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY COMPANY
Connection point (POI)
Highland - Raun 345kV Line Tap
Location
Plymouth County, Iowa
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
14 November 2016
Agreement signed
20 March 2020
Proposed online date
October 2021
Came online
October 2021

Location

Marker shows the centre of Plymouth County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Plymouth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem