Onshore wind project J1109, Cass County

Onshore wind project J1109, Cass County is a 207 MW onshore wind request withdrawn in the MISO interconnection queue, in Cass County, North Dakota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1109
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
Bison 345kV Substation
Location
Cass County, North Dakota
Technology
Wind: 207 MW
Total requested
207 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
August 2021
Withdrawn
March 2020

Location

Marker shows the centre of Cass County; the queue data does not give exact sites.