United States › Grid › Interconnection queues › North Dakota

SOLAR · MISO

Solar project J1588, Cass County

Solar project J1588, Cass County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Cass County, North Dakota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. ConsentedMar 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1588
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
BISON
Location
Cass County, North Dakota
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
30 April 2024
Agreement signed
7 March 2025
Proposed online date
September 2026

Location

Marker shows the centre of Cass County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Cass County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem