United States › Grid › Interconnection queues › North Dakota
ONSHORE WIND · MISOOnshore wind project MPC00500, Cass County
Onshore wind project MPC00500, Cass County is a 379 MW onshore wind request built and operating in the MISO interconnection queue, in Cass County, North Dakota, connecting to Minnkota Power Cooperative.
Request details
- Queue ID
- MPC00500
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Minnkota Power Cooperative
- Connection point (POI)
- Maple River 230 kV Substation
- Location
- Cass County, North Dakota
- Technology
- Wind: 379 MW
- Total requested
- 379 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 3 January 2008
- Proposed online date
- December 2008
- Came online
- December 2008
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Cass County
- Solar + storage project J4105, Cass CountySolar + storage · 500 MW · in study
- Solar + storage project J4106, Cass CountySolar + storage · 500 MW · in study
- Other project J3163, Cass CountyOther · 479 MW · in study
- Solar project J1588, Cass CountySolar · 200 MW · in study
- Solar project J3522, Cass CountySolar · 200 MW · in study
- Onshore wind project J3833, Cass CountyOnshore wind · 200 MW · in study
- Surplus; J1588Battery storage · 200 MW · in study
- Onshore wind project MPC01200, Cass CountyOnshore wind · 49.6 MW · built
- Other project G067, Cass CountyOther · 2.0 MW · built
- Gas project J494, Cass CountyGas · 484 MW · withdrawn
- Onshore wind project J1613, Cass CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project J1109, Cass CountyOnshore wind · 207 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem