United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

ONSHORE WIND Β· MISO

Onshore wind project J966, Putnam County

Onshore wind project J966, Putnam County is a 400 MW onshore wind request withdrawn in the MISO interconnection queue, in Putnam County, Missouri, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J966
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Connection point (POI)
Zachary 345kV Substation
Location
Putnam County, Missouri
Technology
Wind: 400 MW
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
December 2020
Withdrawn
March 2020

Location

Marker shows the centre of Putnam County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Putnam County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem